Groundworks, pad foundations, ESB power and crane lifts

Concrete pad foundations (€14,000 to €28,000 ex VAT for one room), foul/storm drainage (€12,000 to €35,000), ESB three-phase checks and swept-path crane surveys finish before modules leave the factory, letting cranes lift a single classroom in 1 to 2 days over school holidays.

How site preparation runs alongside factory manufacture so steel classroom modules land safely onto your school yard during Easter or Summer holidays.

Free, no obligation. One local supplier prices it, not five.

  • €14,000–€28,000pad foundations (1 room), ex VAT
  • €3,500–€9,500mobile crane day rate, ex VAT
  • 1 to 2 dayscrane lift for 1 classroom
  • Easter / Julzero term-time disruption
Open school building site with concrete foundation piers and a yellow mobile crane positioned for structural lifting

Four site checks to complete before signing a modular order

  1. Gate width & swept-path crane survey. Modular bays travel 3.6 m to 4.2 m wide and up to 14 m long. Measure gate pier widths, check turning radii off the public road and note overhead ESB/Eir lines or protected trees.
  2. Ground bearing & concrete pad foundations. Most Irish yards take reinforced concrete pad foundations or strip beams poured 3 to 4 weeks ahead of delivery. Soft peat, made ground or estuary clay requires trial holes and engineered piling or raft beams.
  3. Foul sewage & storm water invert levels. Confirm depth and fall from the new classroom's en-suite WC and roof downpipes to the existing school manhole. Shallow existing sewers may require a small packaged pumping chamber or SuDS soakaway/attenuation crate.
  4. ESB Networks three-phase MIC capacity. An electrical contractor checks the school's existing Maximum Import Capacity (MIC) and main switchboard spare ways. Adding multiple heat-pump classrooms can trigger an ESB upgrade with a 12 to 20 week utility lead time.

Price my classroom

Four quick taps and our Irish classroom budget appears before we ask for a phone number. One local supplier rings you, not five.

A mainstream modular classroom, about 80 m² (1 classroom), permanent unit & crane lift: €140,000 to €218,000 ex VAT.

Step 1 of 5

What kind of school building?

Pick the closest room type. Exact TGD layout is confirmed at site walk.

How this budget guide is worked out

Permanent turnkey figures reflect going Irish school modular rates (€2,200 to €3,400/m² ex VAT for mainstream rooms and €2,500 to €3,700/m² ex VAT for SEN autism suites) built to 60-year structural design life, NZEB Part L A2/A3 BER, Part M access and TGD-021-5 acoustics on a level yard with reasonable crane access. Unit-and-crane rates exclude groundworks, pad foundations and service connections. Hire rates show weekly rental ex VAT with mobilisation, craneage and foundations noted separately. VAT is 13.5% on qualifying supply-and-install building contracts and 23% on modular hire. Complex ESB upgrades, storm attenuation tanks, road closures or statutory BCAR/FSC/DAC fees are priced after a site walk.

Scheduling safe crane lifts around the Irish school calendar

Safety rules under the Health and Safety Authority (HSA) Construction Regulations strictly separate heavy mobile cranes and articulated wide-load haulage from pupils and parents. Irish modular builders align manufacturing schedules with the school calendar so groundworks stay inside heras-fenced compounds while major crane days land cleanly inside:

  • July and August Summer break. Ideal window for multi-classroom 2-storey blocks, SEN wings and full foul/storm trenching across active yards.
  • Two-week Easter break. Suits single 80 m² mainstream classrooms, SET rooms and temporary decant classroom lifts.
  • October or February mid-term (plus Saturday lifts). Works well for compact 15 to 30 m² SET modules where pads and ducts are already cured.
  • Traffic management & Garda escort permits. Urban schools whose crane must set outriggers on the public street book council road-closure permits 4 to 6 weeks in advance.

School modular questions answered

Can our school use its own local civil contractor for pads and drainage?

Yes. Selecting the 'unit & crane' delivery route saves roughly 22% off the builder's turnkey price while letting your own groundworks contractor pour pads to the supplier's engineer-certified foundation drawings.

What if overhead ESB wires cross the school gate?

ESB Networks can shroud low-voltage lines or arrange a temporary shut-down/diversion on lift day. Flagging overhead cables at the very first yard walk avoids weeks of delay.

How long after crane day can pupils move into the classroom?

Allow 2 to 3 weeks after craning a single classroom (or 5 to 8 weeks on a multi-storey block) for module joint weather-sealing, internal vinyl welding, ramp installation, M&E commissioning, acoustic testing and BCAR sign-off.

Every Irish modular classroom page and guide

modularclassroom.ie is an independent Irish resource, not the Department of Education, the NCSE or a government body, and does not award ASA funding.

Two-storey contemporary school building with modular vertical window bays, warm timber-tone upper cladding, green school lawn and concrete footpath under overcast skies

Check your classroom budget before any call

Select the room type, approximate m² and buy or hire route. When you want a written school proposal, your brief goes to a single modular school supplier in your county.