Planning permission, BCAR, FSC and DAC for modular classrooms
Under S.I. No. 114 of 2021, existing schools can add a once-off single-storey permanent extension up to 210 m² under Class 57 (at least 2 m from party boundaries), or temporary school structures up to 5 years and 30% of existing floor area (max 2 storeys) under Class 20D. Planning exemption never waives Fire Safety Certificate (FSC), Disability Access Certificate (DAC) or BCAR Assigned Certifier sign-off. A Section 5 council declaration (€80, 4 weeks) confirms planning exemption in writing before ordering.
Exact Irish statutory rules separating planning exemptions from mandatory non-domestic Building Control certificates on every school modular build.
Free, no obligation. One local supplier prices it, not five.
- 210 m²Class 57 once-off extension cap
- 5 yearsClass 20D temporary structure cap
- FSC + DACmandatory on every school build
- €80Section 5 written council check

Irish school planning exemptions under S.I. No. 114 of 2021
School exempted development sits in the Planning and Development Regulations 2001 as amended by S.I. No. 114 of 2021. Three classes cover almost every Irish primary and post-primary modular project:
Class 57 (Permanent extension)
- Floor area & height cap
- Max 210 m², strictly single-storey
- Duration & boundary conditions
- Once per school only. Side or rear placement, at least 2 m from party boundary. Must comply with Dept TGDs.
Class 20D (Existing school temporary)
- Floor area & height cap
- Max 30% of existing school GFA, up to 2 storeys
- Duration & boundary conditions
- Maximum 5 years on site. Two-storey units facing homes within 22 m carry overlooking/obscure-glazing limits.
Class 20B (Permitted new school site)
- Floor area & height cap
- Max 50% of permitted permanent GFA, single-storey
- Duration & boundary conditions
- Maximum 5 years on land already holding planning permission for a permanent school.
If the existing school is a Protected Structure, sits in an Architectural Conservation Area (ACA) or has already used its once-off Class 57 allowance, full planning permission is required. Applying for a Section 5 declaration (€80 fee, 4-week council turnaround) protects the Board of Management from enforcement challenges.
Price my classroom
Four quick taps and our Irish classroom budget appears before we ask for a phone number. One local supplier rings you, not five.
A mainstream modular classroom, about 80 m² (1 classroom), permanent turnkey build: €180,000 to €280,000 ex VAT.
How this budget guide is worked out
Permanent turnkey figures reflect going Irish school modular rates (€2,200 to €3,400/m² ex VAT for mainstream rooms and €2,500 to €3,700/m² ex VAT for SEN autism suites) built to 60-year structural design life, NZEB Part L A2/A3 BER, Part M access and TGD-021-5 acoustics on a level yard with reasonable crane access. Unit-and-crane rates exclude groundworks, pad foundations and service connections. Hire rates show weekly rental ex VAT with mobilisation, craneage and foundations noted separately. VAT is 13.5% on qualifying supply-and-install building contracts and 23% on modular hire. Complex ESB upgrades, storm attenuation tanks, road closures or statutory BCAR/FSC/DAC fees are priced after a site walk.
BCAR, Fire Safety Certificate (FSC) and Disability Access Certificate (DAC)
The single biggest programme mistake on Irish school modular builds is assuming that a Class 57 or Class 20D planning exemption removes Building Control paperwork. Because a classroom is a non-domestic institutional building under the Building Control (Amendment) Regulations 2014 (S.I. No. 9 of 2014), four statutory steps remain mandatory:
- Fire Safety Certificate (FSC). Lodged with the local authority fire officer showing structural fire resistance, escape travel distances, compartmentation and IS 3218 fire alarm design. Standard statutory determination is 8 weeks (allow 10 to 14 weeks with requests for further information).
- Disability Access Certificate (DAC). Confirms Part M compliance across approach ramps, door clear widths, accessible WCs, visual contrast and vertical lifts where two-storey.
- BCMS Commencement Notice & Assigned Certifier. Filed on the online Building Control Management System at least 14 days before groundworks start, naming the registered Design Certifier and Assigned Certifier (Architect, Chartered Engineer or Chartered Building Surveyor).
- Certificate of Compliance on Completion (CCC). Signed by both the Builder and Assigned Certifier after airtightness, acoustic, fire-alarm and Part L BER commissioning tests pass. The school cannot legally occupy the classroom until the CCC is validated on the BCMS register.
Related school modular guides
Part M ramps & accessibility1:20 and 1:15 ramp gradients, handrails, landings, thresholds and accessible WCs.
ASA scheme & modular frameworkHow Additional School Accommodation funding and modular frameworks operate.
Groundworks, pads & crane liftsPad foundations, foul/storm drainage, ESB three-phase loads and holiday lifts.
Multi-classroom 2-storey block2 to 6+ classroom blocks for primary, post-primary, ETB and campus sites.
Temporary hire prefab classroomWeekly rental rates, mobilisation costs and the 3 to 5 year buy-vs-hire point.
Classroom costs in IrelandFull Irish ex VAT breakdown for purchase, hire, civils, cranes and fees.School modular questions answered
Can we crane the classroom onto the yard while waiting for the Fire Safety Certificate?
Only under a 7-Day Notice procedure filed with the full FSC application and higher council fee, and even then occupation is illegal until the FSC is granted and the BCAR Completion Certificate is registered.
Do private ECCE crèches get Class 57 or Class 20D exemptions?
No. Class 57 and Class 20D apply strictly to recognised schools. Standalone modular crèches require full commercial planning permission, FSC, DAC and BCAR.
How much do BCAR, FSC and DAC fees add to a single classroom?
Expect €14,000 to €32,000 ex VAT covering council application fees, Design Certifier drawings, Assigned Certifier inspections and pre-completion testing.
How long does a Section 5 planning declaration take?
Local authorities have a statutory 4-week period to issue a Section 5 declaration for a €80 fee.
Every Irish modular classroom page and guide
Room types
TGD & compliance
Regional coverage

Check your classroom budget before any call
Select the room type, approximate m² and buy or hire route. When you want a written school proposal, your brief goes to a single modular school supplier in your county.